Construction is changing the face of Chapel Hill again this summer. This aerial construction photo shows the land after trees were cleared from the site of the future Chapel Hill Retirement Residence on Estes Drive.
Construction is changing the face of Chapel Hill again this summer. This aerial construction photo shows the land after trees were cleared from the site of the future Chapel Hill Retirement Residence on Estes Drive. Contributed

In the summer, it can seem like every street and every corner in southern Orange County has a project under construction.

While building normally ramps up from spring to fall, in Chapel Hill and Carrboro, the summer exodus of UNC students leaves a window of just a few months to start or finish major work. Apartment developers especially aim for late-summer openings to attract returning students.

This year’s projects also have galvanized residents concerned about the loss of long-wooded land and the effects on wildlife habitat and water quality. Chapel Hill and Carrboro have limited vacant land on which to build, leading to more redevelopment and projects on land with steep slopes or environmental challenges.

Two planned logging projects — one of which is still pending — have heightened the concerns.

The owner of 15 acres at Estes Drive and Martin Luther King Jr. Boulevard decided this spring — soon after nearby land was cleared for a retirement community — to harvest the timber from her land. Although developers have approached landowner Kathryn Butler about projects in the past, there is nothing pending at this time.

It’s unclear if Butler plans to replant trees on the land.

Read Next



Read Next

The town also will be making changes to that area this summer, adding bike lanes, sidewalks and an off-road multi-use trail from Martin Luther King Jr. Boulevard to Caswell Road.

A second logging project lies to the west, between the Chapel Hill-Carrboro border and Bolin Creek. There, landowner P.H. Craig plans to harvest the pines from 34 of his roughly 77 acres and replant the land with loblolly pines.

Read Next

Craig is not planning to develop the land, but his project has sparked a community effort to get him to change his mind and sell the land to a preservation group. Residents also have asked the town of Chapel Hill to buy the land or pay Craig the value of his timber, and started a petition to ask the town for stronger tree-protection rules.

Meanwhile, several major projects are beginning or nearing completion:

Chapel Hill

Carraway Village (2).jpg
Carraway Village is transforming 55 acres of mostly forest to a mix of multistory apartments, retail, offices and hotel rooms on Eubanks Road, on Chapel Hill's northern border. Catherine Lazorko clazorko@townofchapelhill.org

Carraway Village

Project description: Developer Northwood Ravin plans to build between 600,000 and 837,000 square feet of apartments, retail, offices and hotel rooms as part of this $100 million project. The 55-acre Eubanks Road site is adjacent to Interstate 40 and N.C. 86.

Happening now: The first, $70 million phase — 403 luxury apartments and 8,800 square feet of retail — is under construction. Northwood Ravin is negotiating with several retail, office and hotel users, and could have some formal announcements soon.

Road construction: Eubanks Road will be widened and new intersections will be built, including at the current N.C. 86/I-40 intersection. The $4.2 million plan also includes sidewalks and bike lanes. The town has agreed to help pay $1.3 million of the cost by delaying annexation and refunding some of the project’s new property taxes.

Residential: Between 43 percent and 75 percent of the project could be apartments, including 50 affordable apartments. The town would get the land slated for affordable housing if those units aren’t built by 2027.

Commercial: Between 15 percent and 44 percent of the project, including a hotel

Office: Between 6 percent and 29 percent of the project

Recreation: 16,000-square-foot Village Green, 24-hour clubhouse, saltwater pool, elevated sky lounge and fitness center

Estimated completion: The first phase is 60 percent complete and expected to open in late 2018/early 2019.

Project website: carrawayvillage.com

Glen Lennox (2).jpg
The first phase of a 20-year construction project will transform the 1950s-era Glen Lennox community (at left) into a mix of more modern housing, office and retail spaces. Catherine Lazorko clazorko@townofchapelhill.org

Glen Lennox

Project description: The town approved a 20-year development agreement in 2014 for Grubb Properties to redevelop this 1950s-era community and its shopping center, located on 70 acres east of the UNC campus.

Happening now: A ceremonial “groundbreaking” was held May 2 for the first phase: the 215-unit Link Apartments, a five-story parking deck and a 6,793-square-foot clubhouse and pool at Brandon and Flemington roads. Grubb Properties is negotiating with the town and Orange County for incentives that could offset the increased cost to build 105,000 square feet of office space now. Construction could start later this year.

Road construction: New neighborhood roads, and transit, bike and pedestrian facilities. Better connections to N.C. 54 and Fordham Boulevard, including a new U-turn and left-turn signals at two Fordham Boulevard intersections.

Residential: Up to 1,500 new apartments, plus existing single-family homes along the eastern property line

Affordable housing: Rent increases are limited for residents who have lived at Glen Lennox for at least five years. The developer also joined the Chapel Hill-Carrboro Chamber of Commerce master leasing pilot program, which would rent some units at market rate to a housing agency or other leaseholder. The leaseholder in turn could sublease apartments to approved renters at a cheaper rate.

Commercial: Up to 150,000 square feet, plus 150 hotel rooms

Office: Up to 600,000 square feet

Recreation: New greenways, open spaces, parks, and a clubhouse with saltwater pool, yoga studio and fitness center

Estimated completion: The first phase could wrap up in a couple of years, but the whole project is expected to take 20 years.

Website: glenlennoxvision.com

Wegmans (2).jpg
Construction could start this summer on the new Wegmans Food Market (at right) on U.S. 15-501 in Chapel Hill. The grocer will replace the former Performance AutoMall (at left), which has moved to a new location near the Streets at Southpoint. Catherine Lazorko clazorko@townofchapelhill.org

Wegmans

Project description: Leon Capital Group is working with Wegmans Food Markets to redevelop the old 14.7-acre Performance AutoMall site between U.S. 15-501 and Old Durham Road. Three smaller lots across Old Durham Road will be used for parking.

Happening now: Hendrick Automotive has moved its dealerships to the Southpoint Automall near The Streets at Southpoint in Durham.

Road construction: Surrounding roads and intersections will be improved. Drivers will enter the site using the Service Road parallel to U.S. 15-501 and driveways on Old Durham Road. A new roundabout is planned just west of Cooper Street. Future road improvements are possible.

Commercial: 130,000 square feet, with 750 parking spaces on both sides of Old Durham Road

Estimated completion: 2019

Website: bit.ly/2No0hLb

Fordham Apts pics (2).jpg
Construction crews have removed a Days Inn and cleared an adjacent lot (left) to make way for the construction of the five- to six-story Fordham Apartments in Chapel Hill's Blue Hill District. Tammy Grubb/Ram Realty tgrubb@heraldsun.com

Fordham Apartments

Project description: Ram Realty Advisers is replacing the former Days Inn hotel and an undeveloped lot at 1300 Fordham Blvd. with a five- to six-story apartment building and parking deck on 3.4 acres.

Happening now: The hotel was demolished this spring, and construction has started. The project is coinciding with the town’s work to create more Booker Creek floodwater storage and green spaces behind the shops on South Elliott Road.

Road construction: Improvements to the Service Road, sidewalks and bike lanes along Fordham Boulevard

Residential: 272 market-rate apartments

Recreation: Pedestrian and greenway connections, public outdoor space

Website: bit.ly/2eIyPL8

Hillstone pics (2).jpg
Crews have cleared the site of a former Crown Honda-Volvo dealership off U.S. 15-501 in Chapel Hill and are preparing to start construction of a multstory apartment complex and parking deck. Tammy Grubb/Leon Capital Group tgrubb@heraldsun.com

Hillstone Chapel Hill

Project description: Two apartment buildings — one five to six stories and the other four stories — and structured parking is replacing the vacant Crown Honda-Volvo dealership and an undeveloped lot. The 6.5-acre site is at 1730 Fordham Blvd., between the Service Road and Legion Road.

Happening now: The vacant dealership has been demolished and construction is underway.

Road construction: A new street will connect the Service Road to Legion Road on the northeastern edge of the property. Streetscape improvements, including sidewalks and bike lanes, are planned for all three streets.

Updates: One lane on Legion Road will be closed Sept. 19-20 from 9 a.m. to 4 p.m. Flaggers will guide traffic through the area.

Residential: 328 market-rate apartments

Recreation: Resort-style pool, fitness and wellness facility

Estimated completion: December 2019

Website: bit.ly/2MQJuz5

Greenfield Place.jpg
Greenfield Place (shown here) is now filled with families and individuals who needed affordable housing in Chapel Hill. A companion project, Greenfield Commons, is under construction and will serve adults 55 and older once completed. Mark Losey Contributed

Greenfield Commons

Project description: The town of Chapel Hill and DHIC Inc. are building 149 affordable family and senior apartments on nine acres of town-owned land beside the Chapel Hill Memorial Cemetery on Legion Road.

Happening now: The project’s first phase — Greenfield Place — opened in January with 80 family apartments. Greenfield Commons, which includes 69 apartments for adults 55 and older, is under construction now.

Residential: 148 apartments, renting to families and seniors for $271 to $870 a month, based on household income and the number of bedrooms.

Recreation: A playground and clubhouse with a kitchen, business center and gathering space

Estimated completion: Greenfield Place is occupied; Greenfield Commons could open by February 2019

Website: dhic.org

CH Retirement Residence art-2
The Chapel Hill Retirement Residence is under construction now on North Estes Drive in Chapel Hill. Neighbors and others took their concerns to the town this spring when the property was clear-cut and blasting began. Chapel Hill Retirement Residence Contributed

Chapel Hill Retirement Residence

Project description: Hawthorne Retirement Group is building a new retirement community on undeveloped land at the corner of Somerset Drive and North Estes Drive.

Happening now: The land has been cleared. Groundwork is progressing, and foundation work has started.

Road construction: New sidewalks, pedestrian crosswalks and bike lanes; a roundabout could be added in the future at the Somerset-Estes intersection.

Residential: 152 suites in a 3- to 4-story building

Recreation: A greenway connecting the site to the Phillips Middle and Estes Elementary school campuses

Estimated completion: September 2019

Website: seniorlivinginstyle.com

Grove-Park_Building-1_SE-Corner
An architect's rendering shows what one of the buildings could look like when the Residences at Grove Park replaced the former Town House Apartments. The property is located between Martin Luther King Jr. Boulevard and 425 Hillsborough St. in Chapel Hill. Eyzenberg and Co. Contributed

Residences at Grove Park

Project description: A mix of four-story apartment buildings and three-story townhouse-style apartments will replace 111 units built in the 1970s between Martin Luther King Jr. Boulevard and 425 Hillsborough St. near downtown. Plans for the 12.3-acre project include a 5-story parking garage and 680 spaces.

Happening now: The former Town House Apartments is being demolished and construction has started.

Grove Park townhouses on Hillsborough St
Some Residences at Grove Park apartments, located off Hillsborough Street, are planned to resemble townhouses. Eyzenberg and Co. Contributed

Road construction: Hillsborough Street improvements include a bus pull off, sidewalks, and a left-turn lane and traffic-calming devices. A high-visibility crosswalk is planned for Martin Luther King Jr. Boulevard.

Residential: 339 apartments (850 beds)

Affordable housing: Six units will be leased to the town for $1 a month for 25 years.

Recreation: Includes a pool, fitness center, and clubhouse

Estimated completion: Anticipated leasing by 2020

Carrboro

South Green pics (2).jpg
Construction of a roundabout and the new South Green retail, restaurant and office project (at right) has temporarily closed South Greensboro Street in Carrboro. Tammy Grubb/Woodhill NC LLC tgrubb@heraldsun.com

South Green

Project description: A retail, restaurant and office complex with four buildings on 5.6 acres at 501 S. Greensboro St.

Happening now: A new roundabout is completed near the entrance to the site. Construction has started on the development.

Road construction: A roundabout at South Greensboro Street, Old Pittsboro Road, and Two Hills Drive, bike lanes and sidewalks

Commercial: 45,000 square feet; announced tenants include Atlas Taco Bar, Craftboro Brewing Depot and Montessori Academy.

Estimated completion: Late 2018

Website: southgreencarrboro.com

Shelton Station pics (2).jpg
The first, commercial phase of Shelton Station is complete and fllling up with tenants in Carrboro. Construction is underway on the second phase, which includes multistory apartments. Tammy Grubb/Legacy Real Property Group tgrubb@heraldsun.com

Shelton Station

Project description: The project is replacing single-family homes with a two-story commercial building along North Greensboro Street, north of Harris Teeter, and a four-story apartment building in the rear of the 2.6-acre lot.

Happening now: The commercial building is being leased, while construction continues on the apartment building.

Residential: 94 apartments

Affordable housing: 20 percent, or 19 apartments

Commercial: 24,000 square feet of ground-floor retail and second-floor office; tenants include the UNC Horizons Program

Recreation: Fitness center, climbing play sculpture

Estimated completion: The commercial building opened in 2017; apartment building could be leased in late 2018

Website: Shelton Station

Tammy Grubb: 919-829-8926; @TammyGrubb